Production Indicators

Title of work

Unit measurement

Monthly volume

Annual volume

Drill

m/m3

289 sqm/ 3677 m3

3470 sqm/44126m3

Fixation

TBK

m2

2097

25159

SVP

pcs

84

1013

SPAC

pcs

2194

26323

Drilled speed:
40-50 sqm per month with arch lining fixation, Spr=14,9-17,1 m2
70-80 sqm per month with combined fixation, Spr=10,5-12,5 m2